1. Approval of Request for Payment-Application No. 6 in the amount of $414,734.85 from D. Wilson Construction Co. awarded contractor for the, "Repairs and Renovations-1st and 2nd Floors to the Former Administration Building", and as certified for payment by project architect, Alcocer Garcia Associates, Inc. and reviewed & initialed by construction manager, Prodigy C-12-029-10-23.
2. Approval of Request for Payment-Application No. 7 in the amount of $302,784.00 from D. Wilson Construction Co. awarded contractor for the, "Repairs and Renovations-1st and 2nd Floors to the Former Administration Building", and as certified for payment by project architect, Alcocer Garcia Associates, Inc. and reviewed & initialed by construction manager, Prodigy C-12-029-10-23.
2. Approval of Request for Payment-Application No. 7 in the amount of $302,784.00 from D. Wilson Construction Co. awarded contractor for the, "Repairs and Renovations-1st and 2nd Floors to the Former Administration Building", and as certified for payment by project architect, Alcocer Garcia Associates, Inc. and reviewed & initialed by construction manager, Prodigy C-12-029-10-23.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2014
- ACCT. #:
- 4-1336-419-40-220-043-0-452
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
PO 698457Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 06/13/2014 10:59 AM |
| Budget and Management | Debbie Tamez | 06/13/2014 11:35 AM |
| Auditor's Office | Monica Salinas | 06/13/2014 05:37 PM |
- Form Started By:
- Rocio Villarreal
- Started On:
- 06/03/2014 04:13 PM
- Final Approval Date:
- 06/13/2014