AI- 45074
Executive Office 6.C.
CC CONSENT
- Meeting Date:
- 06/30/2014
- Submitted By:
- Rebecca Gomez, EXECUTIVE OFFICE
- Department:
Information
CAPTION
Right of Way:
North Alamo Water Supply
* The Estates at Santa Cruz Ranches No. 3:
1). 2" bore 368 feet North of the centerline of Mile 22.5 North will bore Cibolo Drive from east to west.
2). 2" bore 493 feet North of the centerline of Mile 22.5 North will bore Cibolo Drive from east to west.
Terry Palms Subdivision No.2:
1). 2" bore 307 feet South of the centerline of Benito A. Ramirez will bore Terry Road from east to west.
2). 2" bore 477 feet South of the centerline of Benito A. Ramirez will bore Terry Road from east to west.
3). 2" bore 647 feet South of the centerline of Benito A. Ramirez will bore Terry Road from east to west.
4). 2" bore 817 feet South of the centerline of Benito A. Ramirez will bore Terry Road from east to west.
5). 2" bore 987 feet South of the centerline of Benito A. Ramirez will bore Terry Road from east to west.
6). 2" bore 1,157 feet South of the centerline of Benito A. Ramirez will bore Terry Road from east to west.
7). 2" bore 1,357 feet South of the centerline of Benito A. Ramirez will bore Terry Road from east to west.
Vista Ridge Acres Phase V:
1). 2" bore 140 feet South of the centerline of Mile 20 North will bore Norene Road from east to west.
2). 2" bore 392 feet South of the centerline of Mile 20 North will bore Norene Road from east to west.
3). 2" bore 644 feet South of the centerline of Mile 20 North will bore Norene Road from east to west.
4). 2" bore 896 feet South of the centerline of Mile 20 North will bore Norene Road from east to west.
5). 2" bore 1,148 feet South of the centerline of Mile 20 North will bore Norene Road from east to west.
6). 2" bore 1,948 feet South of the centerline of Mile 20 North will bore Norene Road from east to west.
North Alamo Water Supply
* The Estates at Santa Cruz Ranches No. 3:
1). 2" bore 368 feet North of the centerline of Mile 22.5 North will bore Cibolo Drive from east to west.
2). 2" bore 493 feet North of the centerline of Mile 22.5 North will bore Cibolo Drive from east to west.
Terry Palms Subdivision No.2:
1). 2" bore 307 feet South of the centerline of Benito A. Ramirez will bore Terry Road from east to west.
2). 2" bore 477 feet South of the centerline of Benito A. Ramirez will bore Terry Road from east to west.
3). 2" bore 647 feet South of the centerline of Benito A. Ramirez will bore Terry Road from east to west.
4). 2" bore 817 feet South of the centerline of Benito A. Ramirez will bore Terry Road from east to west.
5). 2" bore 987 feet South of the centerline of Benito A. Ramirez will bore Terry Road from east to west.
6). 2" bore 1,157 feet South of the centerline of Benito A. Ramirez will bore Terry Road from east to west.
7). 2" bore 1,357 feet South of the centerline of Benito A. Ramirez will bore Terry Road from east to west.
Vista Ridge Acres Phase V:
1). 2" bore 140 feet South of the centerline of Mile 20 North will bore Norene Road from east to west.
2). 2" bore 392 feet South of the centerline of Mile 20 North will bore Norene Road from east to west.
3). 2" bore 644 feet South of the centerline of Mile 20 North will bore Norene Road from east to west.
4). 2" bore 896 feet South of the centerline of Mile 20 North will bore Norene Road from east to west.
5). 2" bore 1,148 feet South of the centerline of Mile 20 North will bore Norene Road from east to west.
6). 2" bore 1,948 feet South of the centerline of Mile 20 North will bore Norene Road from east to west.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Debbie Tamez | 06/20/2014 09:43 AM |
| Auditor's Office | Monica Salinas | 06/26/2014 05:39 PM |
- Form Started By:
- Rebecca Gomez
- Started On:
- 06/16/2014 09:47 AM
- Final Approval Date:
- 06/26/2014