AI - 46146
7.
DRAINAGE DISTRICT
- Meeting Date:
- 08/25/2014
- Submitted For:
- Lora Briones
- Submitted By:
- Lora Briones, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
A. Request approval to Issue Manual checks for the following Contractor's payment request for construction projects from the 2013 Bond Series after auditing procedures have been completed.
1. Texas Cordia; payment #6; Alamo Expressway Drain; $ 225,785.70.
2. Texas Cordia; payment #2; Edinburg Drain Stubb Out Control Structure; $24,390.
3. FJW Construction; payment #3; J-09 Improvements Phase I $ 45,000.
4. Rojas Construction; payment #4 and Final; RDD North Side Village/Hidden Valley subs. $91,304.30
1. Texas Cordia; payment #6; Alamo Expressway Drain; $ 225,785.70.
2. Texas Cordia; payment #2; Edinburg Drain Stubb Out Control Structure; $24,390.
3. FJW Construction; payment #3; J-09 Improvements Phase I $ 45,000.
4. Rojas Construction; payment #4 and Final; RDD North Side Village/Hidden Valley subs. $91,304.30
BACKGROUND
Fiscal Impact
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Debbie Tamez | 08/21/2014 04:56 PM |
| Final Approval | Monica Salinas | 08/21/2014 05:13 PM |
- Form Started By:
- Lora Briones
- Started On:
- 08/21/2014 04:29 PM
- Final Approval Date:
- 08/21/2014