AI - 47568
11.
DRAINAGE DISTRICT
- Meeting Date:
- 12/02/2014
- Submitted By:
- Claudette Guerrero, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
2013 Bonds:
Request approval to issue manual payment after review and audit procedures are complete on the following items:
Application for Payment No. 3 in the amount of $77,580.00 from Texas Cordia Construction, LLC pertaining to Construction Contract No. 14-004-02-11 Pct.4 Edinburg Drain Stub-Out to South Main Drain Control Structure. PO#624505.
Request approval to issue manual payment after review and audit procedures are complete on the following items:
Application for Payment No. 3 in the amount of $77,580.00 from Texas Cordia Construction, LLC pertaining to Construction Contract No. 14-004-02-11 Pct.4 Edinburg Drain Stub-Out to South Main Drain Control Structure. PO#624505.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Debbie Tamez | 11/25/2014 04:46 PM |
| Final Approval | Monica Salinas | 11/26/2014 05:02 PM |
- Form Started By:
- ccavazos
- Started On:
- 11/25/2014 02:35 PM
- Final Approval Date:
- 11/26/2014