AI - 47733
5.
DRAINAGE DISTRICT
- Meeting Date:
- 12/16/2014
- Submitted By:
- Jaime Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
A.) Requesting approval of final negotiated Agreement for Professional Engineering Services with R. Gutierrez Engineering Corporation as it relates to Pct. 2- "Las Milpas Road Crossing South Floodwater Channel East of FM 907 (Alamo Road)". Approved for negotiations by HCDD1 Board of Directors on November 18, 2014.
B.) Requesting approval of Work Authorization No. 1 with R. Gutierrez Engineering Corporation in the amount of $16,416.00 as it relates to Engineering Services for Pct. 2 -" Las Milpas Road Crossing South Floodwater Channel East of FM 907 (Alamo Road)".
C.) Requesting approval of Work Authorization No. 2 with R. Gutierrez Engineering Corporation in the amount of $2,592.00 as it relates to Surveying Services for Pct. 2 - "Las Milpas Road Crossing South Floodwater Channel East of FM 907 (Alamo Road)".
D.) Approval of subconsultant(s) of TEDSI Infrastructure Group for Phase II of the Master Drainage System for the design and expansion of the lateral drain outfall systems for Precinct No. 1 and Precinct No. 4 in accordance with that certain Agreement by and between Hidalgo County Drainage District No.1 and TEDSI Infrastructure Group dated the 23rd day of March, 2004.
2013 BOND SERIES
E.) Approval of subconsultant(s) of TEDSI Infrastructure Group for Precinct 1 2012 Bond Referendum Improvement Projects in accordance with that certain Agreement by and between Hidalgo County Drainage District No.1 and TEDSI Infrastructure Group dated the 9th day of April, 2013.
F.) Requesting approval of Supplemental Agreement No. 2 to Work Authorization No. 4A with TEDSI Infrastructure Group in the amount of $5,125.98 as it relates to Material Testing for Monte Cristo Drain Control Structure. Pct.1 - 2012 Bond Referendum Improvement Projects.
G.) Requesting approval of Supplemental Agreement No. 2 to Work Authorization No. 4B with TEDSI Infrastructure Group in the amount of $6,394.50 as it relates to Material Testing for Weslaco North Lateral Control Structure. Pct. 1 - 2012 Bond Referendum Improvement Projects.
H.) Requesting approval of Work Authorization No. 17 with TEDSI Infrastructure Group in the amount of $24,507.85 as it relates to Material Testing and Construction Management required for Pct. 1 Spanish Palms Outfall Improvements. Pct. 1 - 2012 Bond Referendum Improvement Projects.
I.) Requesting approval of Supplemental Agreement No. 3 with L&G Engineering to Agreement for Professional Services Pct. 3 - "La Joya Watershed Improvement Project" amendment of Project Team.
B.) Requesting approval of Work Authorization No. 1 with R. Gutierrez Engineering Corporation in the amount of $16,416.00 as it relates to Engineering Services for Pct. 2 -" Las Milpas Road Crossing South Floodwater Channel East of FM 907 (Alamo Road)".
C.) Requesting approval of Work Authorization No. 2 with R. Gutierrez Engineering Corporation in the amount of $2,592.00 as it relates to Surveying Services for Pct. 2 - "Las Milpas Road Crossing South Floodwater Channel East of FM 907 (Alamo Road)".
D.) Approval of subconsultant(s) of TEDSI Infrastructure Group for Phase II of the Master Drainage System for the design and expansion of the lateral drain outfall systems for Precinct No. 1 and Precinct No. 4 in accordance with that certain Agreement by and between Hidalgo County Drainage District No.1 and TEDSI Infrastructure Group dated the 23rd day of March, 2004.
2013 BOND SERIES
E.) Approval of subconsultant(s) of TEDSI Infrastructure Group for Precinct 1 2012 Bond Referendum Improvement Projects in accordance with that certain Agreement by and between Hidalgo County Drainage District No.1 and TEDSI Infrastructure Group dated the 9th day of April, 2013.
F.) Requesting approval of Supplemental Agreement No. 2 to Work Authorization No. 4A with TEDSI Infrastructure Group in the amount of $5,125.98 as it relates to Material Testing for Monte Cristo Drain Control Structure. Pct.1 - 2012 Bond Referendum Improvement Projects.
G.) Requesting approval of Supplemental Agreement No. 2 to Work Authorization No. 4B with TEDSI Infrastructure Group in the amount of $6,394.50 as it relates to Material Testing for Weslaco North Lateral Control Structure. Pct. 1 - 2012 Bond Referendum Improvement Projects.
H.) Requesting approval of Work Authorization No. 17 with TEDSI Infrastructure Group in the amount of $24,507.85 as it relates to Material Testing and Construction Management required for Pct. 1 Spanish Palms Outfall Improvements. Pct. 1 - 2012 Bond Referendum Improvement Projects.
I.) Requesting approval of Supplemental Agreement No. 3 with L&G Engineering to Agreement for Professional Services Pct. 3 - "La Joya Watershed Improvement Project" amendment of Project Team.
BACKGROUND
Fiscal Impact
Attachments
- TEDSI letter_subs Phase II MDS
- TEDSI letter_subs Pct.1 2012 Bond
- R. Gutierrez Agreement Las Milpas
- WA No. 1 Las Milpas
- WA No. 2 Las Milpas
- TEDSI SA No. 2 to WA No.4A
- TEDSI SA No. 2 to WA No. 4B
- TEDSI WA No. 17 Spanish Palms
- L&G SA No. 3 LJWS
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Ortiz | 12/11/2014 08:52 AM |
| Final Approval | Monica Salinas | 12/12/2014 07:12 PM |
- Form Started By:
- Jaime Salazar
- Started On:
- 12/09/2014 01:01 PM
- Final Approval Date:
- 12/12/2014