AI- 48939
Purchasing Department 11.A.
CC CONSENT
- Meeting Date:
- 03/17/2015
- Submitted For:
- Marty Salazar
- Submitted By:
- Letty Saenz, PURCHASING DEPT.
- Department:
- PURCHASING DEPT.
Information
CAPTION
Acceptance and approval of Change Order No. 3 for an extension of seven (7) additional days with (substantial completion date reflecting April 24, 2015) due to weather delays (rain days), with the sum unchanged for Contract No. C-14-067-06-03 with J-CON CONSTRUCTION, LLC as reviewed/approved by project architect, Mata-Garcia Architects, LLP for: Hidalgo County Precinct No. 4 -"Construction of the Linn-San Manuel Emergency Services Facilities" with authority for County Judge, or Court Member to execute document.
BACKGROUND
Change Order #3-J-CON (Mata-Garcia Arch)
Fiscal Impact
- FISCAL YEAR:
- 2015
- ACCT. #:
- 5-1301-419-40-124-136-0-730
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
No budgetary impactfor an extension of seven (7) additional days with (substantial completion date reflecting April 24, 2015) due to weather delays (rain days), with the sum unchanged
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 03/13/2015 04:56 PM |
| Budget and Management | Debbie Tamez | 03/13/2015 04:59 PM |
| Auditor's Office | Monica Salinas | 03/13/2015 05:22 PM |
- Form Started By:
- Letty Saenz
- Started On:
- 03/13/2015 04:36 PM
- Final Approval Date:
- 03/13/2015