Acceptance and approval of Change Order No. 3 for an extension of seven (7) additional days with (substantial completion date reflecting April 24, 2015) due to weather delays (rain days), with the sum unchanged for Contract No. C-14-067-06-03 with J-CON CONSTRUCTION, LLC as reviewed/approved by project architect, Mata-Garcia Architects, LLP for: Hidalgo County Precinct No. 4 -"Construction of the Linn-San Manuel Emergency Services Facilities" with authority for County Judge, or Court Member to execute document. 

BACKGROUND

Change Order #3-J-CON (Mata-Garcia Arch)

Fiscal Impact

FISCAL YEAR:
2015
ACCT. #:
5-1301-419-40-124-136-0-730
FUNDS AVAILABLE Y/N?:
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

No budgetary impact

for an extension of seven (7) additional days with (substantial completion date reflecting April 24, 2015) due to weather delays (rain days), with the sum unchanged

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 03/13/2015 04:56 PM
Budget and Management Debbie Tamez 03/13/2015 04:59 PM
Auditor's Office Monica Salinas 03/13/2015 05:22 PM
Form Started By:
Letty Saenz
Started On:
03/13/2015 04:36 PM
Final Approval Date:
03/13/2015