AI- 52294
Purchasing Department 12.Q.
CC CONSENT
- Meeting Date:
- 12/01/2015
- Submitted For:
- Marcie Jackson
- Submitted By:
- Moises Salazar, PURCHASING DEPT.
- Department:
- COMM. PCT. #1
Information
CAPTION
Ratification of fully executed Change Order No. 7 in connection to contract No. C-14-362-10-28 with 2GS, LLC for the project: -Hidalgo County Precinct #1 -SIOUX ROAD PAVING & DRAINAGE IMPROVEMENTS PROJECT [from Tower Road to Val Verde Road] as recommended by Mr. Raul Sesin, P.E.
BACKGROUND
Additional 20 calendar days due to rain for project completion.
Fiscal Impact
- FISCAL YEAR:
- 2015
- ACCT. #:
- 5-13XX-431-00-121-183-X-721
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
NO additional cost to project; Time extension = 20 calendar days; PO #717811 for 2GS, LLC; funds available as of 11-20-15.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 11/18/2015 12:53 PM |
| Budget and Management | Veronica Ortiz | 11/18/2015 03:47 PM |
| Auditor's Office | Monica Salinas | 11/25/2015 01:55 PM |
- Form Started By:
- moysalazar
- Started On:
- 11/13/2015 04:04 PM
- Final Approval Date:
- 11/25/2015