A. Action to rescind suspension and resume Hidalgo County AIA Contract No. C-13-072A-11-19 with Couric Enterprises, LLC dba Foremost Construction for "Hidalgo County Precinct No. 4 -Construction of a Community Resource Center in San Carlos" by authorizing architect of record Mata Garcia Architects, LLP, to proceed to notify contractor via attached formal letter of Commissioners' Court action to resume construction work as of March 7th, 2016.
B. Acceptance and approval of Change Order No. 5 for modifications to building in the amount of $133,000.00 and an extension of 537 days for Contract No. C-13-072A-11-19 with Couric Enterprises, LLC dba Foremost Construction as reviewed/approved by project architect of record, Mata-Garcia Architects, LLP for: Hidalgo County Precinct No. 4 -"Construction of a Community Resource Center in San Carlos" with authority for County Judge, or Court Member to execute document.
B. Acceptance and approval of Change Order No. 5 for modifications to building in the amount of $133,000.00 and an extension of 537 days for Contract No. C-13-072A-11-19 with Couric Enterprises, LLC dba Foremost Construction as reviewed/approved by project architect of record, Mata-Garcia Architects, LLP for: Hidalgo County Precinct No. 4 -"Construction of a Community Resource Center in San Carlos" with authority for County Judge, or Court Member to execute document.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2016
- ACCT. #:
- X-1342-419-40-124-123-0-730
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Funding through P.O. # 703489 for Contract # C-13-072A-11-19PO# 703489 available bal. as of 3-3-16 30,500
Pct will increase PO amount.
"Per Pct.4, Additional funding needed will come from account# X-1345-431-00-124-029-0-751"
Attachments
- Letter from Architect to Contractor -Rescind Suspension of Contract
- resume
- CO5
- Letter requesting HB1295 Compliance -Foremost Construction
- form
- Change Order Executed.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 03/03/2016 03:22 PM |
| Budget and Management | Veronica Ortiz | 03/03/2016 03:34 PM |
| Final Approval | Monica Salinas | 03/04/2016 08:32 AM |
- Form Started By:
- moysalazar
- Started On:
- 02/26/2016 09:02 AM
- Final Approval Date:
- 03/04/2016