Approval of Payment Application No. 18 in the amount of $3,552.79 sumbitted by IOC Company LLC, awarded contractor for Precinct 3's "Mile 2 North Roadway Project" as certified for payment by project engineer, L&G Engineer, C-14-153-02-17.

BACKGROUND

Funded through PO # 725568.


Fiscal Impact

FISCAL YEAR:
2016
ACCT. #:
6-1315-431-00-123-094-0-721
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Funding available as of 11/8/2016.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 11/07/2016 04:25 PM
Budget and Management Damaris San Miguel 11/07/2016 04:44 PM
Final Approval Monica Salinas 11/10/2016 05:07 PM
Form Started By:
nceballos
Started On:
11/04/2016 04:06 PM
Final Approval Date:
11/10/2016