AI- 57747
Urban County 15.A.
CC - REGULAR
- Meeting Date:
- 12/13/2016
- Submitted For:
- Olga Lerma
- Submitted By:
- Olga Lerma, URBAN COUNTY
- Department:
- URBAN COUNTY
Information
CAPTION
Request approval for the Second Amendment to the 2014 HOME Community Housing Development Organization (CHDO) Program agreement between Hidalgo County Urban County Program and Proyecto Azteca and approval of the addendum (Right of Exercise) with Proyecto Azteca.
BACKGROUND
Proyecto Azteca has requested an amendment to the budget of the 2014 CHDO Agreement in order to allow for reimbursement of soft costs and developer’s fees. The decrease in the overall budget in the amount of $18,537 is due to the fact that the original budget included estimated bid amounts. Now however, Proyecto Azteca has actual bid amounts and as such, the total budget has decreased. The amendment will not change the total contract amount or amount of units to produce in the agreement between the UCP and Proyecto Azteca. The original budget and new budget line items being requested are as follows:
Original Budget
Proposed Budget
Amendment to Agreement Approved by legal December 8, 2016
Original Budget
| HOME Funds | Leveraged Funds | Total Cost | |
| Acquisition | --- | $57,500 | $57,500 |
| Construction Costs | $475,000 | $27,500 | $502,500 |
| Soft Costs | --- | $100,147 | $100,147 |
| Developer's Fee | --- | --- | --- |
| Totals | $475,000 | $185,147 | $660,147 |
Proposed Budget
| HOME Funds | Leveraged Funds | Total Cost | |
| Acquisition | $57,500 | $57,500 | |
| Construction Costs | $423,288 | $27,500 | $450,788 |
| Soft Costs | $21,500 | $81,610 | $103,110 |
| Developer's Fee | $30,212 | $30,212 | |
| Totals | $475,000 | $166,610 | $641,610 |
Amendment to Agreement Approved by legal December 8, 2016
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Ortiz | 12/09/2016 08:45 AM |
| Final Approval | Monica Salinas | 12/09/2016 06:08 PM |
- Form Started By:
- olerma
- Started On:
- 12/08/2016 04:42 PM
- Final Approval Date:
- 12/09/2016