Acceptance and approval of Change Order No. 1 for additional work requested including an additional sixty (60) days in the total amount of $42,590.38, net change order increase of $32,590.38 due to project contingency allowance, under agreement # C-16-321-10-25 with Rigney Construction & Development, LLC, as recommended by Project Engineer Halff Associates, Inc for Precinct 4-"Renovations at M Road Building".

BACKGROUND

Items included in Change Order #1:
Millwork - new work station; Electrical; Polish Concrete Floor; Paint Exterior Letter; HM Doors & Frame w/Hardware; Resilient Cove Base; Accoustic Panels; Transaction Window; Entrance Doors and Frame; Remove/Install Maglocks plus Sixty [60] additional days.

Fiscal Impact

FISCAL YEAR:
2017
ACCT. #:
7-1100-419-00-124-125-0-452
FUNDS AVAILABLE Y/N?:
Y/pending
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

As stated on Change Order, total cost of change order is $42,590.38, $10,000 has been identified from the project contingency allowance the remaining $32,590.38 will be funded through AI-58625 pending approval by commissioners court.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 02/17/2017 10:10 AM
Budget and Management Veronica Ortiz 02/17/2017 10:13 AM
Merlen P. Munoz mmunoz 02/17/2017 11:57 AM
Final Approval Monica Salinas 02/17/2017 05:13 PM
Form Started By:
msalazar
Started On:
02/16/2017 06:04 PM
Final Approval Date:
02/17/2017