CAPTION
Ratification of fully executed Change Order No. 3 in connection with contract No. C-16-281-11-15 -Hidalgo County Precinct #2 -YUMA AVENUE EXTENSION PROJECT(from McColl Rd to 0.16 miles east of McColl Rd) as recommended by project inspector, Eugene Palacios and subject to compliance with HB1295 when and if applicable.
BACKGROUND
Request for 2 additional months of Barricades, Signs, & Traffic Handling. Increase in the amount of $2,530.00.
Fiscal Impact
- CALENDAR YEAR:
- 2017
- ACCT. #:
- 7-1200-431-00-122-126-0-841
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Funding available as of 9/13/17 in the amount of $35,743.48.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | dbetancourt | 09/13/2017 11:18 AM |
| Budget and Management | Veronica Ortiz | 09/13/2017 11:46 AM |
| Final Approval | Monica Salinas | 09/15/2017 05:03 PM |
- Form Started By:
- Erika Zamora
- Started On:
- 09/13/2017 09:54 AM
- Final Approval Date:
- 09/15/2017