AI - 63445
5.
DRAINAGE - CONSENT
- Meeting Date:
- 01/30/2018
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the fully executed Change Order No. 1, reflecting an increase of 23 construction calendar days and $23,420.00 in connection with the construction contract No. C-HCDD1-17-005-02-21 - Hidalgo County Drainage District No. 1 “Pharr-McAllen South Drain Outfall Improvements at USIBWC Main Floodway” as recommended by project engineer, S&B Infrastructure, LTD, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., C.F.M., subject to compliance with HB1295.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 01/26/2018 05:29 PM |
- Form Started By:
- moysalazar
- Started On:
- 01/24/2018 01:17 PM
- Final Approval Date:
- 01/26/2018