CAPTION
Ratification of the fully executed Change Order No. 3, reflecting a credit in the amount of ($47,732.56), in connection with contract No. C-HCDD1-17-015-04-18 with Texas Cordia Construction, LLC for - Hidalgo County Drainage District No. 1 "Precinct No. 1 Mile 13 1/2 N. Rd. and FM 1015 Area Drainage Improvements Project Phase 2 & 3" as recommended by project engineer, Urban Infrastructure Group, Inc., and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., C.F.M., subject to compliance with HB1295 if and when applicable.