Skip to main content

AgendaQuick™

View Agenda Item

AI - 65605
7.
DRAINAGE - CONSENT
Meeting Date:
07/17/2018
Submitted For:
Jaime Salazar
Submitted By:
Moises Salazar, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

Information

CAPTION

Ratification of the fully executed Change Order No. 1 reflecting an increase of  twenty (20) calendar days, in connection with contract No. C-HCDD1-18-020-05-08 -Hidalgo County Drainage District No. 1 "HCDD1 J-09 Drain Improvements Phase III -Roadway & Field Crossings" with Castle Enterprises, LLC, as recommended by project engineer TEDSI Infrastructure Group, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM, subject to compliance with HB1295 when and if applicable.

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Monica Salinas 07/13/2018 04:55 PM
Form Started By:
moysalazar
Started On:
07/09/2018 03:37 PM
Final Approval Date:
07/13/2018