CAPTION
Subject to HB 1295 Compliance, requesting consideration and action to award and enter into a construction contract with GNH Company, LLC in the amount of $180,523.02. UCP Fiscal Years 27, 28 & 29 (2014, 2015 & 2016) Elsa-Street Improvement funds will be utilized.
BACKGROUND
The Urban County Program has requested and received bids for the City of Elsa – Street Improvements. CSJ Group prepared the specification packages and bids were received and opened at the Hidalgo County – Purchasing Department on July 17, 2018. After review the project engineer recommended GNH Company, LLC as the lowest of eight (8) qualified bidders. (See attached recommendation letter, bid tabulation sheet, contract, certificate of liability insurance and HB 1295 form).
Contractor: GNH Company, LLC
Contract Amount: $180,523.02
Funds Available: $ 83,030.10 FY 27 (2014) Street Improvements
$ 85,011.63 FY 28 (2015) Street Improvements
$101,380.14 FY 29 (2016) Street Improvements
Total Funds: $269,421.87
APPROVED AS TO FORM
Atlas, Hall & Rodriguez
By: Stephen L. Crain
Date: April 28, 2016
Contractor: GNH Company, LLC
Contract Amount: $180,523.02
Funds Available: $ 83,030.10 FY 27 (2014) Street Improvements
$ 85,011.63 FY 28 (2015) Street Improvements
$101,380.14 FY 29 (2016) Street Improvements
Total Funds: $269,421.87
APPROVED AS TO FORM
Atlas, Hall & Rodriguez
By: Stephen L. Crain
Date: April 28, 2016
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Ortiz | 07/25/2018 04:58 PM |
| Final Approval | Monica Salinas | 07/27/2018 05:56 PM |
- Form Started By:
- olerma
- Started On:
- 07/25/2018 03:55 PM
- Final Approval Date:
- 07/27/2018