CAPTION
Approval to issue payment on the following items proceeding review & compliance of contract terms & conditions:
CP 130
Budget: 005 New Administration Bldg
A. Application for Payment No. 3 in the amount of $249,998.40 from Bullard Construction, Inc. pertaining to Construction Contract No. HCDD1-18-002-05-22.
Project Engineer: Halff and Associates Engineering
PO#634554
CP 130
Budget: 005 New Administration Bldg
A. Application for Payment No. 3 in the amount of $249,998.40 from Bullard Construction, Inc. pertaining to Construction Contract No. HCDD1-18-002-05-22.
Project Engineer: Halff and Associates Engineering
PO#634554
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 08/10/2018 03:12 PM |
- Form Started By:
- ccavazos
- Started On:
- 08/09/2018 02:43 PM
- Final Approval Date:
- 08/10/2018