AI - 66443
8.
DRAINAGE DISTRICT
Meeting Date:
09/04/2018
Submitted For:
Moises Salazar
Submitted By:
Monica Salinas, EXECUTIVE OFFICE
Department:
DRAINAGE DISTRICT

Information

CAPTION

Requesting approval of Change Order No. 1 reflecting an increase in the amount of $60,000.00 and ten (10) additional calendar days, in connection with contract No. C-HCDD1-18-002-05-22 -Hidalgo County Drainage District No. 1 "New Administration Building" with Bullard Construction, Inc., as recommended by project engineer Halff Associates, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM, subject to compliance with HB1295 when and if applicable.

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Monica Salinas 09/01/2018