AI- 67079
Purchasing Department 12.Y.
CC CONSENT
Prct. 4
- Meeting Date:
- 10/09/2018
- Submitted For:
- Joseph Palacios
- Submitted By:
- Nick Perez, COMM. PCT. #4
- Department:
- COMM. PCT. #4
Information
CAPTION
Approval of application for payment No. 8 in the amount of $334,977.54; project 10th Street Extension submitted by contractor, Texas Cordia Construction, LLC through Contract C-17-218-01-16 as reviewed by project manager, Ricardo Gallaga, L&G Consulting Engineers, Inc.
BACKGROUND
Fiscal Impact
- CALENDAR YEAR:
- ACCT. #:
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Fiscal impact addressed through Purchase Order #774917Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 10/05/2018 02:41 PM |
| Budget and Management | Veronica Ortiz | 10/05/2018 02:42 PM |
| Final Approval | Monica Salinas | 10/05/2018 05:17 PM |
- Form Started By:
- Nick Perez
- Started On:
- 10/05/2018 01:42 PM
- Final Approval Date:
- 10/05/2018