AI - 67601
7.
DRAINAGE - CONSENT
- Meeting Date:
- 11/20/2018
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Requesting approval of Change Order No. 2 reflecting an increase of thirty (30) additional calendar days, in connection with contract No. C-HCDD1-18-015-04-24 -Hidalgo County Drainage District No. 1 "J-09 Drain Improvements Phase II - Roadway & Field Crossings" with Rigney Construction, LLC, as recommended by project engineer TEDSI Infrastructure Group, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM, subject to compliance with HB1295 when and if applicable.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 11/16/2018 05:13 PM |
- Form Started By:
- moysalazar
- Started On:
- 11/08/2018 02:32 PM
- Final Approval Date:
- 11/16/2018