CAPTION
1. Approval to rescind action previously taken by Commissioner's Court on 1/9/2019 AI#68359;
2. Acceptance and approval to execute AIA Document A133-2009 Guaranteed Maximum Price Amendment No. 1 between Hidalgo County and contractor, Erickson Construction, LLC. for the "Pct 2 Las Milpas Park Youth Facility" Project through Contract No. C-17-324-07-17, in the amount of $73,459.42 with authority to issue a Notice to Proceed [NTP], subject to legal counsel's final review and approval.
2. Acceptance and approval to execute AIA Document A133-2009 Guaranteed Maximum Price Amendment No. 1 between Hidalgo County and contractor, Erickson Construction, LLC. for the "Pct 2 Las Milpas Park Youth Facility" Project through Contract No. C-17-324-07-17, in the amount of $73,459.42 with authority to issue a Notice to Proceed [NTP], subject to legal counsel's final review and approval.
BACKGROUND
GMP Amendment No. 1 is for the upgrade of a waterline necessary to comply with City of Pharr Subdivision plat requirements.
Fiscal Impact
- CALENDAR YEAR:
- 2019
- ACCT. #:
- 9-1351-451-22-122-141-0-730
- FUNDS AVAILABLE Y/N?:
- Y/Pending
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Funding pending rollover of Certificates of Obligation by the Auditor's Office. Funding available in year 2018 as of 1/4/19 is $651,461.28.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 03/01/2019 05:05 PM |
- Form Started By:
- Erika Zamora
- Started On:
- 02/22/2019 01:44 PM
- Final Approval Date:
- 03/01/2019