AI - 73076
5.A.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 11/05/2019
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the fully executed Change Order No.7 reflecting an increase in the amount of $36,615.51, and one hundred and fifty-three (153) additional construction calendar days, in connection with contract No. C-HCDD1-18-020-05-08 -Hidalgo County Drainage District No. 1 "HCDD1 J-09 Drain Improvements Phase III -Roadway & Field Crossings" with Castle Enterprises, LLC, as recommended by project engineer TEDSI Infrastructure Group, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM. (subject to compliance to HB1295)
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 11/01/2019 05:58 PM |
- Form Started By:
- moysalazar
- Started On:
- 11/01/2019 11:02 AM
- Final Approval Date:
- 11/01/2019