CAPTION
Requesting approval of Change Order No. 8 (C-18-199-02-12) with Texas Cordia Construction, LLC for the Hidalgo County Precinct #2 -Regional Linear Park Project - Section 2 (from Ridge Road to Hall Acres Road) as recommended by project engineer, Saul Muñoz, P.E..
BACKGROUND
Request for contract increase in the amount of $200,718.00 due to additional rip rap required to eliminate erosion caused by rising waters during heavy rainfall events.
Fiscal Impact
- CALENDAR YEAR:
- 2019
- ACCT. #:
- 9-1315-452-00-122-110-8-740
- FUNDS AVAILABLE Y/N?:
- Y/Pending
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Funding pending approval of AI#74122 CC 1/28/20 in the amount of $225,000.00.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 01/24/2020 12:43 PM |
| Budget and Management | Veronica Ortiz | 01/24/2020 12:44 PM |
| Final Approval | Monica Salinas | 01/24/2020 05:52 PM |
- Form Started By:
- Erika Zamora
- Started On:
- 01/23/2020 06:29 PM
- Final Approval Date:
- 01/24/2020