DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 02/11/2020
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the fully executed Change Order No. 3 reflecting an increase in the amount of $14,825.00, and Twenty one (21) additional construction calendar days, in connection with contract No. C-HCDD1-19-064-09-03 -Hidalgo County Drainage District No. 1 "Hidalgo Drain (Military Road Crossing) -2018 Bond Referendum Project #13" with Mor-Wil, LLC, as recommended by project engineer, SAMES, Inc., and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM., subject to compliance to HB1295.