AI - 78434
6.B.
DD-REGULAR AGENDA REGULAR MTG
- Meeting Date:
- 11/24/2020
- Submitted For:
- Raul Sesin
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
CAPTION
Requesting approval of Change Order No. 3 reflecting an increase in the amount of $288,286.75, and One Hundred and Twenty (120) additional construction calendar days, in connection with contract No. C-HCDD1-19-074-11-26 -Hidalgo County Drainage District No. 1 "Mission Lateral (Section I) -2018 Bond Referendum project #26" with Saenz Brothers Construction as recommended by project engineer, Damien B. Tijerina, P.E., L&G Engineering (subject to compliance to HB1295).
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 11/20/2020 04:40 PM |
- Form Started By:
- moysalazar
- Started On:
- 11/20/2020 02:42 PM
- Final Approval Date:
- 11/20/2020