CAPTION
Ratification of the fully executed Change Order No. 6 reflecting Twenty-One (21) additional construction calendar days, in connection with contract No. C-HCDD1-19-077-12-03 -Hidalgo County Drainage District No. 1 "Hidalgo County Precinct No. 4 -J-09 Phase IV Rural Drainage Development -2012 Bond Projects" with Mor-Wil, LLC, as recommended by project engineer, Jose Noe Saldivar, P.E., HCDD1 Engineer IV, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM.,
BACKGROUND
Fiscal Impact