CAPTION
Alamo Expressway Drain-Budget 320:
Approval to issue payment on the following items proceeding review & compliance of contract terms & conditions:
1. Acceptance of Certificate of Substantial Completion from Castle Enterprises, LLC pertaining to Construction Contract No. HCDD1-18-047-09-25 Alamo Expressway Drain Improvements.
2. Acceptance of Certificate of Construction Completion from Castle Enterprises, LLC pertaining to Construction Contract No. HCDD1-18-047-09-25 Alamo Expressway Drain Improvements.
3. Application for Payment No. 5-Retainage in the amount of $49,778.20 from Castle Enterprises, LLC pertaining Construction Contract No. 18-047-09-25-Alamo Expressway Drain Improvements. Project Engineer: Jose N. Saldivar, P.E. PO#636128.
Approval to issue payment on the following items proceeding review & compliance of contract terms & conditions:
1. Acceptance of Certificate of Substantial Completion from Castle Enterprises, LLC pertaining to Construction Contract No. HCDD1-18-047-09-25 Alamo Expressway Drain Improvements.
2. Acceptance of Certificate of Construction Completion from Castle Enterprises, LLC pertaining to Construction Contract No. HCDD1-18-047-09-25 Alamo Expressway Drain Improvements.
3. Application for Payment No. 5-Retainage in the amount of $49,778.20 from Castle Enterprises, LLC pertaining Construction Contract No. 18-047-09-25-Alamo Expressway Drain Improvements. Project Engineer: Jose N. Saldivar, P.E. PO#636128.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 12/30/2020 03:24 PM |
- Form Started By:
- ccavazos
- Started On:
- 12/29/2020 05:02 PM
- Final Approval Date:
- 12/30/2020