Requesting approval of Change Order No 7 [a Decrease under #C-19-017-11-15] with 2GS, LLC dba Earthworks Enterprise for the Hidalgo County Precinct #2 - Dicker Road Reconstruction Project from (23rd Street to Jackson Road) as recommended by the project engineer, Saul Muñoz, P.E.

BACKGROUND

CO #7-Relocate proposed signal pole @ 23rd St, Add 2 well gates, Add 17ft of RCB, introduce 3rd traffic control change, replace exisiting pedestrian elements @ McColl Rd, Replace 18 pedestrian two way indicators, increase rip rap quantities due to plan error, and negogiate asphalt millings.

Change Order 6 will decrease the contract ($407,003.83)

Fiscal Impact

CALENDAR YEAR:
2021
ACCT. #:
1-1315-431-00-122-062-0-721
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Change Order No. 7 reduces the construction contract amount so a PO cancellation will be submitted to Purchasing.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 01/29/2021 05:10 PM
Final Approval Monica Salinas 01/29/2021 05:16 PM
Form Started By:
Erika Zamora
Started On:
01/29/2021 03:16 PM
Final Approval Date:
01/29/2021