AI - 80060
6.D.
DD-REGULAR AGENDA REGULAR MTG
- Meeting Date:
- 03/23/2021
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
CAPTION
Requesting approval of Change Order No. 2 reflecting an increase in the amount of $443,151.48, and additional one hundred and fifty (150) construction calendar days, in connection with the Contract No. C-HCDD1-20-026-06-23 -"PD Lateral (Phase I) -2018 Bond Referendum Project #29" with Mor-Wil, LLC, as recommended by Project Engineer, Izaguirre Engineering Group, LLC.
BACKGROUND
HB1295 Form has been submitted.
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 03/19/2021 05:15 PM |
- Form Started By:
- moysalazar
- Started On:
- 03/18/2021 10:28 AM
- Final Approval Date:
- 03/19/2021