CAPTION
Ratification of the fully executed Change Order No. 2 reflecting an increase in the amount of $6,000.00, and additional Sixty three (63) construction calendar days, in connection with the Contract C-HCDD1-20-040-09-08 -"3 3/4 Mile Rd. & Schuerbach Rd -2018 Bond Referendum Project #2" with Gonzalez Engineering & Management, LLC, as recommended by Project Engineer, Javier Hinojosa Engineering, and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.
BACKGROUND
Form HB1295 has been submitted.
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 07/09/2021 05:33 PM |
- Form Started By:
- moysalazar
- Started On:
- 07/02/2021 01:42 PM
- Final Approval Date:
- 07/09/2021