View Agenda Item

AI - 81844
3.A.
DD-CONSENT AGENDA REGULAR MTG
Meeting Date:
07/27/2021
Submitted For:
Jaime Salazar
Submitted By:
Rocio Villarreal, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

CAPTION

Ratification of the fully executed Change Order No. 2 reflecting Sixty (60) additional calendar days, in connection with Construction Contract C-HCDD1-20-041-09-15-"Sunflower Drain -2018 Bond Referendum Project #36" with  Mor-Wil, LLC, as recommended by Project Engineer, Izaguirre Engineering Group, and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 07/23/2021 05:20 PM
Form Started By:
Rocio Villarreal
Started On:
07/23/2021 03:52 PM
Final Approval Date:
07/23/2021