AI - 82123
5.D.
DD-CONSENT AGENDA REGULAR MTG
- Meeting Date:
- 08/24/2021
- Submitted For:
- Jaime Salazar
- Submitted By:
- Rocio Villarreal, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
CAPTION
Ratification of the fully executed Change Order No. 3 reflecting a net increase of $6,720.00, and an additional twenty-eight (28) construction calendar days, in connection with Contract C-HCDD1-20-044-09-15, "Old La Blanca Rd & Mile 10 N-2018 Bond Referendum-Project #28" with Venser Contractors, LLC, and as recommended by Project Engineer, Guzman & Munoz Engineering & Surveying, and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 08/20/2021 05:20 PM |
- Form Started By:
- Rocio Villarreal
- Started On:
- 08/20/2021 09:04 AM
- Final Approval Date:
- 08/20/2021