CAPTION

Mile 9N & FM 1015 - Budget 524
1. Approval of Application for Payment No. 4 in the amount of $37,427.76 from Mor-Wil, LLC pertaining to Construction Contract HCDD1-20-065-11-18. Project Engineer Halff & Associates PO#641649.

PD Lateral Phase II - Budget 529
2. Approval of Application for Payment No. 6 in the amount of $380,246.85 from Mor-Wil, LLC pertaining to Construction Contract HCDD1-20-029-06-23. Project Engineer Izaguirre Engineering PO#640212.