CAPTION

Ratification of fully executed Change Order No. 8 in connection with Contract No. C-19-017-11-05 with 2GS, LLC for the Pct 2 Dicker Road Project as recommended by project engineer B2Z Engineering, LLC, subject to compliance with HB1295 when/if applicable.

BACKGROUND

Change Order No. 8 is for additional time (51 Days) and 3 months of barricades for a total increase in the amount of $5,756.07.
 

Fiscal Impact

CALENDAR YEAR:
2021
ACCT. #:
1-1315-431-00-122-062-0-721
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Funding available as of 1/21/22 in the amount of $75,533.80.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal Dina Trevino 01/21/2022 03:25 PM
Budget and Management Veronica Ortiz 01/21/2022 03:32 PM
Final Approval Monica Salinas 01/22/2022 11:00 AM
Form Started By:
Erika Zamora
Started On:
01/20/2022 10:44 AM
Final Approval Date:
01/22/2022