CAPTION
Acceptance and approval of Supplemental Agreement No. 1 for services under Work Authorization No. 1, through Contract No. C-HCDD1-21-026-06-01 with B2Z Engineering, LLC, resulting in an estimated cost increase of $95,937.18 for, "Mission-McAllen Rado Alternate Ph I-2018 Bond Referendum Project #25." (subject to Legal Review)