CAPTION
Ratification of approved and fully executed Change Order No. 1, in connection with the project -"Weslaco Drain Improvements (Proposed Additional 10x10 Box with Gate)", reflecting Ninety-seven (97) additional construction calendar days to Contract No. C-HCDD1-21-017-06-01, with Castle Enterprises, LLC, as recommended by Project Manager, Omar Anzaldua, Jr., P.E., CFM, PMP, CCM, HCDD1 Assistant District General Manager, and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM (subject to compliance with HB1295).