CAPTION

Mission Lateral - Budget 526
Requesting acceptance and approval of Certificate of Substantial Completion and Certificate of Construction Completion from H&R Lease Service, LLC pertaining to Mission Lateral Section II Construction Contract C-HCDD1-20-042-09-08. Project Engineer: L&G Consulting Engineers, Inc. PO#640759

South Lateral Drain - Budget 534
Requesting approval of Application for Payment No. 12 in the amount of $37,519.42 pertaining to Construction Contract No. C-HCDD1-20-009-07-07 South Lateral Drain. Project Engineer: L&G Consulting Engineers, Inc. PO#640528

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 04/01/2022 04:42 PM
Form Started By:
Alvaro Chuc
Started On:
04/01/2022 02:55 PM
Final Approval Date:
04/01/2022