CAPTION

Ratification of the approved and fully executed Change Order No.  9 with Mor-Wil, LLC (C-HCDD1-20-041-09-15) reflecting an additional fourteen (14) construction calendar days, "Sunflower Drain -2018 bond Referendum Project No. 36" and as recommended by Project Engineer, Izaguirre Engineering Group, LLC, and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM. 

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 09/02/2022 03:57 PM
Form Started By:
Rocio Villarreal
Started On:
09/01/2022 03:30 PM
Final Approval Date:
09/02/2022