CAPTION
Ratification of approved and fully executed Change Order No. 3, in connection with the project "South Lateral Drain Improvements Phase I’’, reflecting an increase of Ninety (90) additional construction calendar days to Contract No. C-HCDD1-20-009-07-07, with Castle Enterprises, LLC, as recommended by Project Engineer, Asst. District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 10/14/2022 04:06 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 10/12/2022 11:42 AM
- Final Approval Date:
- 10/14/2022