AI - 88247
6.E.
DD-REGULAR AGENDA SPECIAL MTG
Meeting Date:
11/15/2022
Submitted For:
Jaime Salazar
Submitted By:
Enriqueta Zambrano, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

Information

CAPTION

Requesting approval of Change Order No. 1 reflecting an increase in the amount of $873,498.70, and One Hundred and Twenty (120) additional construction calendar days, in connection with Contract No. C-HCDD1-21-054-01-11 -"Mile 9 N. & FM 1015 -Package 1B Improvements-2018 Bond Referendum  Project No. 24'' with Mor-Wil, LLC, as recommended by Project Engineer, Asst. District General Manager, Yvette Barrera, PE, CFM
 