AI - 88573
4.A.
DD-CONSENT AGENDA SPECIAL MTG
Meeting Date:
11/29/2022
Submitted For:
Jaime Salazar
Submitted By:
Rocio Villarreal, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

Information

CAPTION

Ratification of the approved and fully executed Change Order No.  6 with Saenz Brothers Construction (C-HCDD1-21-027-07-27) reflecting an additional thirty (30) construction calendar days, "Mission Lateral Ph III(Proposed Widening of Ditch from Bentsen Palm Drive to the West of Wagon City 2 Subdivision)-2018 Bond Referendum Project #26" and as recommended by Project Engineer, L&G Engineering, and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.   

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 11/23/2022 03:37 PM
Form Started By:
Rocio Villarreal
Started On:
11/22/2022 04:53 PM
Final Approval Date:
11/23/2022