Ratification of the approved and fully executed Change Order No. 3 with Clore Equipment, LLC (C-HCDD1-22-001-03-08) reflecting an increase of thirty three (33) calendar days to the Alamo Expressway Drain Extension Improvements Project as recommended by Project Engineer, Omar Anzaldua, PE, Asst. General Manager and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.