AI - 89822
5.G.
DD-REGULAR AGENDA SPECIAL MTG
Meeting Date:
03/07/2023
Submitted For:
Jaime Salazar
Submitted By:
Enriqueta Zambrano, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

Information

CAPTION

1.  Requesting approval of the final negotiated Professional Engineering Service Agreement for the provisions of Project Management & Construction Materials Testing with B2Z Engineering, for the project, "Main Flood Water Channel 2016 GLO Project", Contract No. C-HCDD1-22-047-03-07 and as approved for negotiations on 08/18/22 AI-87051. (Subject to final legal review)

2. Acceptance and approval of Work Authorization No. 1 to provide Professional Engineering Services on Project Management & Construction Materials Testing in the amount of $563,440.60 as submitted by B2Z Engineering for the project, "Main Flood Water Channel 2016 GLO Project", through Contract No. C-HCDD1-22-047-03-07

BACKGROUND

Special Services:
Project Management Services $460,647.60
Construction Materials Testing $102,793.00
                                         Total $563,440.60

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 03/03/2023 05:08 PM
Form Started By:
Enriqueta Zambrano
Started On:
02/27/2023 10:56 AM
Final Approval Date:
03/03/2023