CAPTION
Ratification of approved and fully executed Change Order No. 9, in connection with the project "Jackson Rd Drain Phase I -2018 Bond Referendum Project No. 16’’, reflecting an increase of Sixty (60) additional construction calendar days to Contract No. C-HCDD1-20-034-08-11, with RG Enterprises, LLC dba G&G Contractors, as recommended by Project Engineer, Quintanilla Headley & Associates.
BACKGROUND
Contract Time Extension -60 additional days due to Weather & Supplier Delays. (pump fittings, elbows, etc.)
Project completion date: June 24, 2023 for Change Order 9
Project completion date: June 24, 2023 for Change Order 9
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 04/28/2023 04:08 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 04/27/2023 03:46 PM
- Final Approval Date:
- 04/28/2023