CAPTION
Requesting approval of Change Order No.2, reflecting an increase in the amount of $83,854.00, and Ninety (90) additional construction calendar days, in connection with the project "Mission-McAllen Rado Phase I -2018 Bond Referendum Project No. 25’', Contract No. C-HCDD1-21-023-07-27, with Gonzalez Engineering & Management, LLC, as recommended by Project Engineer, B2Z Engineering, LLC.