CAPTION
Ratification of approved and fully executed Change Order No. 3, reflecting a decrease of $5,434.00 and an increase of 40 construction calendar days in connection with the project "FM 493 & County Road - Phase 1 Subdivision Drainage Improvements - 2018 Bond Referendum Project No. 12", Contract No. C-HCDD1-22-032A-08-18, with Saenz Brothers Construction, LLC., as recommended by Project Engineer Sames, Inc. and approved by HCDD1 Assistant District General Manager, Yvette Barrera, P.E., CFM.