CAPTION
Requesting approval of Supplemental Agreement No. 3 to the Professional Engineering Service Agreement & to the Work Authorization No. 1 for ''4 ½ Mile Rd. & N. Doffing Rd., -2018 Bond Referendum Project No. 3 with Contract (C-HCDD1-19-053-11-05), with CSJ Group, to reflect a revised period of service to end on May 31, 2024 (subject to final legal review and compliance with HB1295).
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 12/08/2023 05:18 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 12/04/2023 04:25 PM
- Final Approval Date:
- 12/08/2023