Ratification of approved and fully executed Change Order No. 4 reflecting an increase of sixty(60) additional construction calendar days, for the project "Mile 9 N. & FM 1015 -Package 1B Improvements-2018 Bond Referendum Project No. 24'', Contract No. C-HCDD1-21-054-01-11 - with Mor-Wil, LLC, as recommended by  Project Engineer, Halff Associates, Inc.

BACKGROUND

Completion date as per change order 4, February 06, 2024