AI - 93794
5.D.
DD-REGULAR AGENDA SPECIAL MTG
- Meeting Date:
- 01/09/2024
- Submitted For:
- Omar Anzaldua Jr.
- Submitted By:
- Enriqueta Zambrano
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Requesting approval of Change Order No.1, reflecting an increase in the amount of $102,090.12 and 40 additional construction calendar days for the project ''Weslaco Drain Improvements (Proposed Additional 10' x 10' Box with Gate Structure)'', Contract No. (C-HCDD1-21-017-R-05-02), with Mor-Wil, LLC, as recommended by Project Engineer, B2Z Engineering.
BACKGROUND
Project completion date for this change order, January 30, 2024
Fiscal Impact