CAPTION
Rincon de Encinos Phase 3 - Budget 010
1. Approval and Acceptance of Certificate of Substantial Completion and Certificate of Construction Completion from McAllen Multi Service pertaining to Construction Contract C-HCDD1-23-033-08-08 Rincon De Encions. Project Engineer: HCDD1 Omar Anzaldua, Jr., PE, CFM PO#648190
2. Approval of Application for Payment No. 7 Retainage in the amount of $38,877.64 and $212.44 in interest from McAllen Multi Service pertaining to Construction Contract C-HCDD1-23-033-08-08 Rincon De Encions. Project Engineer: HCDD1 Omar Anzaldua, Jr., PE, CFM PO#648190
East Mercedes - Budget 510
3. Approval of Application for Payment No. 9 in the amount of $88,372.80 from RBM Contractors pertaining to Construction Contract C-HCDD1-22-051-01-17 East Mercedes. Project Engineer: HCDD1 Yvette Barrera, PE, CFM PO#647299
Mile 10 North & Baseline - Budget 520
4. Approval of Application for Payment No. 7 in the amount of $84,517.99 from RBM Contractors pertaining to Construction Contract C-HCDD1-23-014-04-26 Mile 10 N & Baseline. Project Engineer: Quintanilla Headley, PO#648064
South I Rd - Budget 533
5. Approval of Application for Payment No. 4 in the amount of $91,700.10 from Mor Wil, LLC pertaining to Construction Contract C-HCDD1-22-060-11-29 South I Road. Project Engineer: B2Z Engineering PO#647343
South Lateral Drain Structure - Budget 534
6. Approval of Application for Payment No. 8 in the amount of $39,854.25 from Mor Wil, LLC pertaining to Construction Contract C-HCDD1-22-033-07-12 South Lateral Drain Structure. Project Engineer Omar Anzaldua, Jr, PE, CFM PO#646381
7. Approval and Acceptance of Certificate of Substantial Completion and Certificate of Construction Completion from Mor Wil, LLC pertaining to Construction Contract C-HCDD1-22-033-07-12 South Lateral Drain Structure. Project Engineer Omar Anzaldua, Jr, PE, CFM PO#646381
8. Approval of Application for Payment No. 9 Retainage in the amount of $198,622.81 and $648.77 interest from Mor Wil, LLC pertaining to Construction Contract C-HCDD1-22-033-07-12 South Lateral Drain Structure. Project Engineer Omar Anzaldua, Jr, PE, CFM PO#646381
1. Approval and Acceptance of Certificate of Substantial Completion and Certificate of Construction Completion from McAllen Multi Service pertaining to Construction Contract C-HCDD1-23-033-08-08 Rincon De Encions. Project Engineer: HCDD1 Omar Anzaldua, Jr., PE, CFM PO#648190
2. Approval of Application for Payment No. 7 Retainage in the amount of $38,877.64 and $212.44 in interest from McAllen Multi Service pertaining to Construction Contract C-HCDD1-23-033-08-08 Rincon De Encions. Project Engineer: HCDD1 Omar Anzaldua, Jr., PE, CFM PO#648190
East Mercedes - Budget 510
3. Approval of Application for Payment No. 9 in the amount of $88,372.80 from RBM Contractors pertaining to Construction Contract C-HCDD1-22-051-01-17 East Mercedes. Project Engineer: HCDD1 Yvette Barrera, PE, CFM PO#647299
Mile 10 North & Baseline - Budget 520
4. Approval of Application for Payment No. 7 in the amount of $84,517.99 from RBM Contractors pertaining to Construction Contract C-HCDD1-23-014-04-26 Mile 10 N & Baseline. Project Engineer: Quintanilla Headley, PO#648064
South I Rd - Budget 533
5. Approval of Application for Payment No. 4 in the amount of $91,700.10 from Mor Wil, LLC pertaining to Construction Contract C-HCDD1-22-060-11-29 South I Road. Project Engineer: B2Z Engineering PO#647343
South Lateral Drain Structure - Budget 534
6. Approval of Application for Payment No. 8 in the amount of $39,854.25 from Mor Wil, LLC pertaining to Construction Contract C-HCDD1-22-033-07-12 South Lateral Drain Structure. Project Engineer Omar Anzaldua, Jr, PE, CFM PO#646381
7. Approval and Acceptance of Certificate of Substantial Completion and Certificate of Construction Completion from Mor Wil, LLC pertaining to Construction Contract C-HCDD1-22-033-07-12 South Lateral Drain Structure. Project Engineer Omar Anzaldua, Jr, PE, CFM PO#646381
8. Approval of Application for Payment No. 9 Retainage in the amount of $198,622.81 and $648.77 interest from Mor Wil, LLC pertaining to Construction Contract C-HCDD1-22-033-07-12 South Lateral Drain Structure. Project Engineer Omar Anzaldua, Jr, PE, CFM PO#646381
BACKGROUND
Fiscal Impact
Attachments
- McAllen Multi Serv 010 Substantial
- McAllen Construction Completion
- McAllen Multi Serv 010
- RBM 510
- RBM 520
- Mor Wil 533
- Mor Wil 534
- Mor Wil Substantial Completion
- Mor Wil Construction Completion
- Mor Wil 534
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 03/15/2024 04:57 PM |
- Form Started By:
- Alvaro Chuc
- Started On:
- 03/15/2024 12:51 PM
- Final Approval Date:
- 03/15/2024